“How long will it take?” is the first question on every RFQ and the most commonly misanswered. The honest answer has two parts: the factory’s build time, which is short and predictable, and the component lead time, which is neither. Any date quoted without checking both is a guess dressed up as a schedule.
Prototype timelines: 15 days is real, with conditions
A prototype build in 15 days from receipt of build-ready files is achievable. It is our standard for prototype programmes. The conditions decide everything. Files must be genuinely build-ready, with no footprint mismatches and no unresolved BOM alternates. All components need to be available from stock or short-lead sources. Test requirements must be defined upfront, not invented mid-build. Each unresolved item adds days, and a single allocated part can add weeks regardless of how fast the line runs.
Build prototypes on production lines with production inspection: same SPI, same full AOI, same test. A bench-built prototype with hand inspection tells you nothing about what volume production will yield, and qualifying a design on data that does not transfer is worse than no prototype at all.
What actually sets the production date
For production runs, placement time is rarely the constraint. Four high-speed lines at 130,000 placements per hour each can place an enormous volume of boards per shift; the schedule is set by:
- Component availability. The longest-lead part on the BOM sets the start date. Standard passives: days. Common ICs: one to three weeks. Allocated or obsolete parts: months, or never.
- BOM health. Single-source parts, end-of-life notices, and unapproved alternates each add a sourcing cycle. Our pre-order BOM risk review, run before quoting, surfaces these while the schedule can still absorb them.
- Test development. New functional test fixtures take engineering time. Reusing proven fixtures from a prototype programme shortens this to nearly zero, which is another reason to prototype with your production supplier.
- Consignment logistics. If you consign parts, inbound freight, customs and incoming verification sit on the critical path. Ship early, verify on arrival, and hold safety stock on the long-lead lines.
How to get a date you can plan against
Send complete files and a complete BOM with manufacturer part numbers. Ask the supplier to confirm lead times on every line before quoting a date. Approve alternates for the risky lines upfront. And treat the first article from a prototype run as schedule insurance: it validates the files, the fixtures and the test procedure before the volume order commits the calendar.